Create Assignments

Create Resource Assignments from the Assignments Gantt (Beta)

Note: Users given assignments this way are also added to the project in the company's Directory.

 In Beta

This feature is in beta and available for customers using the Resource Planning tool.

 Tip

You can also create this by creating a copy of an existing item on the Assignments Gantt.

  1. Navigate to the Company level Resource Planning tool.

  2. Click Assignments and select Gantt (Beta).

  3. On the list, right click the project, category or subcategory for the assignment and select New Assignment.
    Note: You can also hover over the project, category, or subcategory and click the vertical ellipsis icon-ellipsis-vertical.png and select New Request.

  4. Fill out the 'Details' information. Show/Hide Fields

    • Project. Select the project from the drop-down menu.

    • Category. Select the category.

    • Subcategory. Select the subcategory.

    • Labor. Select the assignee(s) from the drop-down menu.

    •  In Beta

      Equipment. Select equipment from the drop-down menu.

      To add equipment to assignments, your project must have the following configurations:

  5. Fill out the 'Schedule' information. Show/Hide Fields

    • Start Date. Enter the date the work assignment starts.

    • End Date. Enter the date the work assignment ends.

    • Move the 'Set Assignment by Start Week and Duration' toggle to the ON icon-toggle-on.png position. Then enter the Start Time and End Time.
      OR
      Move the 'Set Assignment by Allocation' toggle to the ON icon-toggle-on.png position. Then enter the Percent Allocated for the request.

    • Work Days. Mark the checkbox for each work day for the request.

    • Overtime. If an assignment allows for overtime, move the 'Overtime' toggle to the ON icon-toggle-on.png position.

      1. Enter the 'Overtime Rates' per day of the week.
        For example, overtime on a weekday may be 1.5 for time and a half, and 2 for double time on the weekend.

      2. Enter the Pay Split.

  6. Fill out the Additional Information. See Configure Custom Fields for Resource Planning.

  7. Optional: Enter Scope of Work to describe the scope of work.

  8. Optional: Enter Assignment Instructions to provide additional instructions.

  9. Optional: Enter Comments.

  10. Click Create.

 Tip

Click the undo icon-gantt-undo.png icon to undo an action. Click the redo icon-gantt-redo.png icon redo a previously undone action.