Configure Displayed Information

Steps

  • Adjust List and Timeline Ratio

  • Configure Displayed Information

  • Group by Project or Resource

  • Expand and Collapse Projects, Categories, and Subcategories

  • View Timeframe, Zoom In and Out

Adjust List and Timeline Ratio

  1. Navigate to the Company level Resource Planning tool.

  2. Click Assignments and select Gantt (Beta).

  3. Hover over the divider that separates the grid and the graph.

  4. Click the divider and move it to the desired location using a drag-and-drop operation.
    Adjust Width

Configure Displayed Information

  1. Navigate to the Company level Resource Planning tool.

  2. Click Assignments and select Gantt (Beta).

  3. Click the Projects or Resources view.
    New Gantt Resource Project Picker

  4. Click the table settings Icon Ag Grid Table Filter Menu icon.

    • Projects View

      Show / Hide Steps

      • Click the Columns tab.

        • Move the toggle Icon Toggle On ON or Icon Toggle Off OF show or hide columns on the gantt chart.

          • Job Title

          • Project Start Date

          • Project End Date

          • Task Start Date

          • Task End Date

        • Click the grip Icon Reorder Grip icon and drag the column into the desired display order.

      • Click the Gantt Chart tab.

        • Move the toggle Icon Toggle On ON or Icon Toggle Off OF show or hide details in the Gantt bars.

          • Project Information

          • Allocation Information

          • Weekends

          • Time Off

          • Resources Not in Group

        • Row Height

          • Select Small, Medium, or Large.

        • Click and move the slider to adjust the size for the Task Border Radius.

    • Resources View

      Show / Hide Steps

      • Move the toggle Icon Toggle On ON or Icon Toggle Off OFF position to show or hide details in the Gantt bars.

        • Project Information

        • Allocation Information

        • Time Off Information

        • Hide Weekends

      • Click and move the slider to adjust the size for the following settings:

        • Row height in the Gantt

        • Task Border Radius

      • Select the Assignment Bar colors.

        • Allocation Percentage

        • Job Titles

        • Overtime

        • Percentage

        • Project

      • Select the Cell Units.

        • Allocation (percentage)

        • Cost

        • Hours

        • Man Days- Hours divided by paid shift hours.

Group by Project or Resource

  1. Navigate to the Company level Resource Planning tool.

  2. Click Assignments and select Gantt (Beta).

  3. Select to see information grouped by Resources or Projects.
    New Gantt Resource Project Picker

Expand and Collapse Projects, Categories, and Subcategories

  1. Navigate to the Company level Resource Planning tool.

  2. Click Assignments and select Gantt (Beta).

  3. Next to the project, category, or subcategory, take one of the following actions:

    • Click the expand Icon Expand Materials Esticom icon to expand the information

    • Click the collapse Icon Arrow Collapse icon to collapse the information

 Tip

To expand and collapse assignments for all projects or resources, click the expand Icon Vertical Carets Collapse or collapse Icon Vertical Carets Expand icon next to the 'Project Name' or 'Resource' heading.

View Timeframe, Zoom In and Out

  1. Navigate to the Company level Resource Planning tool.

  2. Click Assignments and select Gantt (Beta).

  3. Configure your timeframe:

    • Select the date, and select the timeframe from the neighboring dropdown menu.

    • Click the zoom in Icon Zoom In Magnifying Glass icon or zoom out Icon Zoom Out Magnifying Glass icon to view the Gantt from a single day, up to many years.