Edit a Coordination Issue

The Coordination Issues tool allows you to manage BIM model conflicts efficiently. While most data fields can be modified directly, note that 'Source File,' 'Created From,' 'Date Created,' and 'Attachments' are permanent records and cannot be edited.

Things to Consider

  • Required User Permissions

  • Additional Information:

    • Browser Refresh: If you edit an issue with the Procore BIM Plugin while Procore is open in a browser, you must refresh the page to see updates.

    • Editable Fields: You can modify the Title, Description, Location, Due Date, Priority, Assignee, Watchers, Trade, Type, and any custom fields.

    • Status: To learn about issue status, see What statuses are available in the Coordination Issues tool?

    • Syncing: Edits made in Procore sync automatically with the Procore BIM Plugin.

From the Coordination Issues Tool ​​​​​​

Edit a Coordination Issue

  1. Navigate to the project's Coordination Issues tool in Procore.

  2. Click the Issue link to view its details in the side panel.

  3. In the General tab, update the fields as needed.

     Note

    Changes save automatically. In the General tab, you can edit text fields and drop-down menus, but you cannot edit Attachments.

  4. Optional: Add comments or images:

    1. Click the Activity tab.

    2. Enter a comment in the Type a message or @mention someone box.

    3. Upload an image by clicking Attach Image.

    4. Save the activity by clicking Submit.

  5. Optional: Move or elevate the issue to another Procore tool by clicking the Icon Vertical Ellipsis Box Pfcp icon to choose a menu option:

  6. Optional: If an issue was moved or elevated an issue and you want to change that:

    • To reopen a coordination issue that was moved to an observation, click Reopen. The issue status changes from Moved to Observation to Open.

    • To unlink a coordination that was elevated to an RFI, click Unlink RFI. The issue status changes from Elevated to Open.

  7. When finished, click the Icon Markup Close X icon to close the side panel.

From the Procore BIM Plugin

  1. Open Navisworks® and your model on your computer. See Getting Started: Procore BIM Plugin for Coordination Issues.

  2. With the Procore tab selected, click Issues List.

  3. In the All Issues or Assigned to Me list, hover over the issue to edit.

  4. Click Info.

  5. Click in any editable field to modify the information. Changes save automatically when you click out of the field.

From the Procore Documents Plugin for Autodesk®

  1. Open Revit® on your computer.

  2. Navigate to a 3D view in the Revit® project browser.

  3. Click the Procore tab.

  4. Click Coordination Issues.

  5. In the Coordination Issues side panel, select the Procore project.

  6. On the coordination issue, click the Information Icon Info3 icon.

  7. Click any editable field and modify the information. Changes save automatically when you click out of the field.