Bulk Edit Resource Assignments
Things to Consider
You can manage user visibility of assignments with assignment request statuses. See Configure Assignment Request Statuses for Resource Planning.
Assignment alerts are not sent to assignees when bulk editing resource assignments.
Steps
You can bulk edit assignments from the following places:
Assignments List
Assignments List (Beta)
Assignments Boards
Assignments Gantt
Bulk Edit Assignments from the Assignments List
Navigate to the Company level Resource Planning tool.
Click Assignments and select Assignments List.
Mark the checkboxes for the assignments that you want to edit.
Click Batch Actions.

Select the assignment information you want to edit:
End Date. Enter the date the work assignments end.
End Time. Enter the time the assignments end.
Percent Allocation. Enter the percent allocation for the assignments.
Person. Select the person you want to assign to all the selected assignments.
Project. Select the project that the assignments are for.
Start Day. Enter the date the assignments start.
Start Time. Enter the time the assignments start.
Status. Select the assignment status.
[Custom Fields]. Enter information for any assignment custom fields.
Click Save.
Note: To send an assignment alert for these changes, keep the checkboxes marked, then follow these steps.
Bulk Edit Assignments from the Assignments List (Beta)
Beta
This feature is in beta and available for customers using the Resource Planning tool.
Navigate to the Company level Resource Planning tool.
Click Assignments and select Assignments List (Beta).
Mark the checkboxes for the assignments, then click the edit
icon.Update the assignment information.
Click Update.
Send Assignment Alert Updates
After you create or update an assignment, send an alert to the assignee.