Considerations
Limitations
Projects with more than 100,000 drawing revisions can not be connected.
Project connections can only be initiated by the receiving project.
A receiving project can only connect to one sending project. However, note that a sending project can support multiple receiving project connections.
Markups from the sending project’s drawings are not copied to the receiving project.
Custom fields are not included when copied from the sending project.
Connections can only be made with ‘active’ projects. Inactive projects are not supported.
GovCloud accounts will not be able to participate in a project connection.
Drawings only sync one-way from a sending project to a receiving project. It is not possible for the receiving project to upload drawings to a connected drawing set.
If projects are disconnected, they cannot be reconnected.
If projects are disconnected, the receiving project can not connect to a new sending project.
Click here to return to Connection Manager Tutorials.