Add Quantities to a Timesheet (Android)

Background

Production quantities are a measurable amount of work on a construction project. For example, cubic yards of concrete, number of light fixtures, or linear feet of piping. In Procore, there are two types of production quantities:

  • Budgeted production quantities refers to the measurable amount a team plans to install on a project.

  • Installed production quantities refers to the actual amount installed on a project by a point in time.

After installed production quantities have been entered in a timesheet, they can be tracked against the imported budgeted production quantities using the Production Quantity Report.

Things to Consider

Prerequisites

Steps

After you create your timesheet, perform the following actions:

  1. Tap Submit.

  2. Under 'Select an Option', Submit and Add Quantities.
    submit-and-add-quantities.png

  3. Tap Add Quantities.

  4. Tap Add Units.

  5. In the Units Installed Today field, enter the number of items installed for the day.

  6. Optional: Enter any notes.

  7. Tap Apply to save your changes.