Edit an Inter Project Materials Transfer
In Beta
This feature is currently in beta.
This feature is currently in beta.
To move materials to a new project, create an inter project materials transfer.
Once the inter project transfer finalized, Procore automatically creates a shipment for the receiving project. When the receiving project finalizes a receipt with the associated shipment, the transfer status is updated to 'Transfer Complete' or 'Transfer Received' in the relevant project.
After you finalize a transfer and the status is 'Final', you can only edit the following fields:
Attach files
Custom Fields
Notes
'Quantity Available' counts are updated when the transfer is finalized and the status is 'Final'.
Quantities of Pre-Transfer 'Acceptable' materials that were transferred from your project are removed from the 'Quantity Available' in your inventory.
Quantities of 'Unacceptable' and 'Damaged' Materials are already excluded from the 'Quantity Available' in your inventory.
Navigate to the project's Materials tool.
Click the Transfers tab.
Click the transfer number.
Edit the transfer information.
Click Edit in the 'Transfer Information' header.
Update the transfer information.
Click Save.
For each line item, enter the transfer information.
Click Edit in the 'Items' header.
Click the 'Add Items' search bar to add items from your inventory.
For each item, update the transfer.
Click Close.
Save or submit the transfer.
Click Save as Draft to save the transfer as a draft.
Click Submit to submit the transfer for approval.