Create Daily Construction Report Entries

Background

The Daily Construction Report section allows you to track the total number of workers and hours worked for each vendor, company, and trade on a project. You can configure additional categories for workforce labor using the company-level Admin tool for use on projects. See How do I enable additional workforce labor types for the Daily Log?

Things to Consider

  • Required User Permissions:

  • Additional Information:

    • Entries made by collaborators are marked as 'pending' until approved by an administrator.

    • There are additional workforce labor categories that can be added to the Daily Construction Report in the Daily Log tool. For example, Women, Veteran, Minority, First-Year Apprentice, Local (City), and Local (County). In order to track hours for these additional workforce labor types, these fields must first be configured in the Daily Log section of the company level Admin tool, and then applied to one or more projects. See How do I enable additional workforce labor types for the Daily Log?
      Note
      : Once configured and applied, the Workforce Hours column with an Add Hours link is visible in the Daily Construction Report section.

Steps

  1. Navigate to the project's Daily Log tool.

  2. Scroll to the Daily Construction Report section.
    You can also use the left navigation menu to quickly navigate to the Daily Construction Report section.

  3. To create an entry, add information to the fields.

    Note: Click the caret icon > to expand and v to collapse the field names and their descriptions below.

    • #: A read-only field that displays the sequential entry number (for example, #1 for the first entry created and #2 for the second entry created).

    • Company: Select the company name from the dropdown menu.
      Note: Companies must be added to the project's Directory tool to be selected in this dropdown menu.
      See Add a Company to the Project Directory.

    • Trade: Select the trade associated with the entry from the dropdown menu. You can only select from the trades already added to the project. See Add a Custom Trade.

    • Location: Select the project location from the dropdown menu.

    • Foreman: Enter the total number of foremen on-site that day followed by the total number of hours worked.

    • Journeyman: Enter the total number of journeymen on-site that day followed by the total number of hours worked.

    • Apprentice: Enter the total number of apprentices on-site that day followed by the total number of hours worked.

    • Others: Enter the number of any other workers and the total number of hours worked.

    • Comments: Enter any comments or additional information that further describes the entry (if required).

    • Attachments: Attach any additional files to the entry. To attach files, do one of the following:

      • Click Attach File(s) and then drag-and-drop a file from your computer to the Drag and Drop your File(s) area.

      • Click Upload Files to select a file from your computer.

     Tip

    Certain fields in the Daily Construction Report log can be configured as required, optional, or hidden in the company level Admin tool.

  4. (Optional:) If additional 'Workforce Hours' fields have been configured in the company level Admin tool, the 'Add Hours' link is visible.
    Dl Dcr Add Hours

    1. Click the Add Hours link.

    2. Enter the hours for each category you want to track hours for.
      Dl Workforce Hours

    3. Click Add Hours to confirm.

  5. Click Create.
    The log entry is created.