Manual Entry/Itemized Manual Entry
To update the Forecast To Complete calculation:
In the Forecast To Complete column, click the linked amount or the horizontal ellipsis
icon.
Note: In the enhanced Budget and Forecasting tables, click the linked amount or the drop-down menu. For details on opting into the beta programs, see the banner at the top of this page.
Under Calculation Method, choose the Manual Entry/Itemized Manual Entry option.

In the enhanced Budget and Forecasting tables, select this option from the drop-down menu in the Forecast To Complete column or the Calculation Method menu within the 'Forecast To Complete' panel. For details on opting into the beta programs, see the banner at the top of this page.
In the enhanced Budget and Forecasting tables, click the bottom panel view
icon or side panel view
icon in the 'Forecast To Complete' panel to dock it to the bottom or the side of the table. For details on opting into the beta programs, see the banner at the top of this page.
Optional: Enter any relevant information in the Notes box.
Note: In the enhanced Budget and Forecasting tables, the Notes box is only available in the 'Forecast To Complete' panel. It cannot be accessed via the drop-down menu in the Forecast To Complete column. For details on opting into the beta programs, see the banner at the top of this page.
Optional: To add line items, click Add new line item.
For each line item, enter the following:
Description
Enter a description for the new line item.
Quantity
Enter a quantity. By default, the entry is set to 1.
Units
Select a unit of measure (see Which units of measure are included on Procore's master list?). The default selection ‘ls’ (lump sum).
Unit Cost
Enter the cost per unit. For example, type: 100.00. The default entry is zero (0.00).
Amount
Enter the total cost associated with the line item. This is the number of units multiplied by the unit cost.
Add line items as needed.
Depending on the experience you are using, click Done or the close
icon to save your changes and return to the budget.
Lump Sum Entry/Lump Sum Manual Entry (Forecasting Tab)
This Lump Sum Entry method should be used when you want to input a single figure to forecast the remaining cost at completion for a specific budget code in a project's budget. In the Budget tab, Procore populates the 'Lump Sum Entry' amount with the 'Forecast To Complete' amount. If you want to input a different amount, you must edit the amount in the 'Forecasting' tab. To learn how to set up a forecasting view, see Set Up a New Forecasting View.
To update the Forecast To Complete calculation:
Click the Forecasting tab.
In the Forecast To Complete column, click the horizontal ellipsis
icon.
Note: In the enhanced Forecasting table, click the linked amount or the drop-down menu. For details on opting into the beta program, see the banner at the top of this page.
Under Calculation Method, choose the Lump Sum Entry/Lump Sum Manual Entry option.
Note: In the enhanced Forecasting table, select this option from the drop-down menu in the Forecast To Complete column or the Calculation Method menu within the 'Forecast To Complete' panel. You can also click the bottom panel view
icon or side panel view
icon in the 'Forecast To Complete' panel to dock it to the bottom or the side of the table. For details on opting into the beta program, see the banner at the top of this page.
Enter a lump sum amount in the text box.
Because your lump sum entry overrides the 'Forecast to Complete' amount in the budget, it is important to understand the implication that using this calculation can have on your overall budget forecast.
Optional: Enter any relevant information in the Notes box.
Note: In the enhanced Forecasting table, the Notes box is only available in the 'Forecast To Complete' panel. It cannot be accessed via the drop-down menu in the Forecast To Complete column. For details on opting into the beta program, see the banner at the top of this page.
Depending on the experience you are using, click Done or the close
icon to save your changes and return to the budget.
Monitored Resources
The 'Monitored Resources' column forecasts your projected costs based on the resource rates and time, and then introduces resources, applying a time and date, and adding a unit cost and utilization rate for resources within a budget code. Procore automatically draws down the 'Forecast To Complete' amount over time.
To update the Forecast To Complete calculation:
In the Forecast To Complete column, click the linked amount or the horizontal ellipsis
icon.
Note: In the enhanced Budget and Forecasting tables, click the linked amount or the drop-down menu. For details on opting into the beta programs, see the banner at the top of this page.
Under Calculation Method, choose the Monitored Resources option.

In the enhanced Budget and Forecasting tables, select this option from the drop-down menu in the Forecast To Complete column or the Calculation Method menu within the 'Forecast To Complete' panel. For details on opting into the beta programs, see the banner at the top of this page.
In the enhanced Budget and Forecasting tables, click the bottom panel view
icon or side panel view
icon in the 'Forecast To Complete' panel to dock it to the bottom or the side of the table. For details on opting into the beta programs, see the banner at the top of this page.
Optional: Enter any relevant information in the Notes box.
Note: In the enhanced Budget and Forecasting tables, the Notes box is only available in the 'Forecast To Complete' panel. It cannot be accessed via the drop-down menu in the Forecast To Complete column. For details on opting into the beta programs, see the banner at the top of this page.
Optional: To add additional entries, click Add new line item.
For each line item, enter the following:
Description
Enter a description for the new resource line item.
Examples include:
Project Manager Level 1, Level 2
Office Trailer Rental
Temporary Toilet Facilities
Temporary Storage Container Rental
Start Date
Select a start date for the resource's line item.
End Date
Select an end date for the resource's line item.
Units Remaining
Choose Weeks or Months. Weeks is the default selection. Procore uses today's date to automatically calculate the 'Units Remaining' value and continues to draw down the remaining amount at the end of each week or month.
Unit Cost
Add the cost per unit. The default setting is zero (0.00). For example, type: 100.00
Utilization
Enter the percent of the resource that is utilized within the given duration of the line item.
Your entry in the previous column determines how the value in each column populates.
Note: Procore does not permit you to pro-rate costs. For example, 8 days is equal to 2 weeks, not 1.14 weeks.
Column Name | Calculation |
Calculated Unit Cost | Utilization Rate * Unit Cost |
Forecast to Complete | Calculated Unit Cost * Units Remaining |
Planned | Calculated Unit Cost * Total Units This value applies to the start and end date that you specificed. |
Add line items as needed.
Depending on the experience you are using, click Done or the close
icon to save your changes and return to the budget.