Why and how do I create a custom budget code description for Procore's Project Financials tools?
Background
The 'Create Budget Code' feature in Procore's Project Financials tools lets your team create custom budget code descriptions to satisfy different use cases. Some examples include:
Capture Granular Detail About a Single Budget Code
Improve the Readability of Your Budget Code Descriptions
Shorten Budget Code Descriptions to Conserve Space
To learn how to create custom budget code descriptions, see the Answer below.
Capture Granular Detail About a Single Budget Code
If you want to capture more granular detail about a single budget code, review this example.
Example
Let's assume your Procore project is using only the default segment items in Procore's Work Breakdown Structure (WBS). In the 'Cost Code' segment, which is based on the CSI The MasterFormat is an organization standard that defines the master list of Divisions, Sections, and Section Titles for construction project specifications in the United States and Canada. It is authored by the Construction Standards Institute (CSI) and Construction Specifications Canada (CSC)._S_ee CSI MasterFormat®.
When the budget code for a financial line item is associated with an allowance
An allowance is an amount included in a contract sum to cover the costs of any items not specified in the contract.When the budget code for a financial line item is associated with a contingency
A contingency is an amount set aside in a contract to cover the costs of any additions to the scope of work due to unknown risk factors.
To address this scenario, you can use Procore's custom budget code description option to create two (2) descriptions for a single budget code. This allows your team to distinguish between the budget code is used for an allowance versus when its used for a contingency. In the illustration below:
The budget code is: F1.17-010.M
The custom budget code description is: Floor1.Allowance.Materials
The default budget code description is: Floor1.Contingency.Materials
You can also create additional budget code descriptions for each budget code to suit your organizations specific needs.

Improve the Readability of Your Budget Code Descriptions
When creating segments using Procore's A budget code structure is a sequence of segments used to build meaningful budget codes in accordance with the pattern established by your organization. In Procore's Work Breakdown Structure, the budget code structure for a company or project can be comprised of multiple segments.
Example
Using the same example as above, you can also use Procore's custom budget code description option to simplify and improve readability of your budget codes. This can improve readability of your budget codes, as shown in the illustration below:
The budget code is: F1.17-010.M
The custom budget code description is: Flr 1 Materials Allowance
The custom budget code description is: Flr 1 Materials Contingency
The illustration below shows you how the custom descriptions can improve readability.