Can I export Procore budget modifications to an integrated ERP system?

 Phased Release: Budget Changes

Some ERP integrated clients may have already transitioned from Budget Modifications (Legacy) to the new Budget Changes experience. The legacy experience will continue to be available until October 16, 2023. To learn more about the timeline for migration, see: Common Questions.

Choosing to use the new Budget Changes experience will not impact the function of your ERP integration, or the steps in this tutorial. If you encounter a step with directions regarding Budget Modifications, and you have already adopted Budget Changes, please take the same action in Budget Changes as you would in Budget Modifications.

To learn more about the new Budget Changes experience, see About Budget Changes.

Answer

Yes. If your company's has enabled the ERP Integrations tool and you are using Procore with a supported , you can export budget modifications as detailed in the table below.

Task

Supported

Not Supported

Viewpoint® Spectrum®: Viewpoint® Spectrum®
Budget modifications appear as estimate changes on a Change Request in Viewpoint® Spectrum®.

icon_checkmark_h17.png

Vista®
Budget modifications sync with estimate changes in Vista® .

icon_checkmark_h17.png

QuickBooks® Desktop
Budget modifications appear below the 'Budget Modifications' label as line items on the Estimate.

icon_checkmark_h17.png

Sage 100 Contractor®
Budget modifications appear as 'Approved Estimate Changes' and update the 'Imported Estimate'.

icon_checkmark_h17.png

Sage 300 CRE®
Budget modifications appear as 'Approved Estimate Changes' and update the 'Imported Estimate'.

icon_checkmark_h17.png

CMiC
Budget modifications will update the 'Budgeted Cost Amount'.

icon_checkmark_h17.png